Home / Civil Engineering / Engineering Economics :: Discussion

Discussion :: Engineering Economics

  1. The estimate based on a detailed quantity survey and furnishes the most accurate and reliable estimate possible is known as

  2. A.

     Conceptual estimate

    B.

     Definitive estimate

    C.

     Probabilistic estimate

    D.

     None of these

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided