  1. A construction estimate is used

  2. A.
    to judge tentatively or approximate value of the project
    B.
    to produce a statement of the approximate cost
    C.
    to decide an approximation of the value of the project and not the exact cost.
    D.
    None of these

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.