Home / Civil Engineering / Engineering Economy :: Discussion

Discussion :: Engineering Economy

  1. Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

  2. A.
    To have a check on a definitive cost estimate.
    B.
    To check qoutations from contractors and/or sub contractors.
    C.
    To compute target estimate for the owner while drawings and specifications are in initial stage.
    D.
    All of these.

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.