  1. The project contractor relies on the cost of the estimate :

  2. A.
    for submission of a competitive bid for a lumpsum contract
    B.
    for a unit price contract
    C.
    for preparation of a definitive estimate to help negotiate contract.
    D.
    All of these

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.