Discussion :: Engineering Economy
-
Which method is adopted to develop an approximate or conceptual estimate for perimeter works for buildings from the following:
A.
Base unit method
|
B.
Cost per function method
|
C.
Cost per square metre method
|
D.
Cost per cubic metre method
|
E.
Cost per linear metre method
|
Answer : Option E
Explanation :
No answer description available for this question.
Be The First To Comment