Discussion :: Engineering Economy
-
Pick up the correct method adopted for developing the approximate or conceptual estimates from the following :
A.
Base unit method
|
B.
Cost per function method
|
C.
Cost per square metre
|
D.
Cost per linear unit
|
E.
All of these
|
Answer : Option E
Explanation :
No answer description available for this question.