  1. A pre-tensioned concrete member of section 200 mm x 250 mm contains tendons of area 500 mm2 at centre of gravity of the section. The prestress in the tendons is 1000 N/mm2. Assuming modular ratio as 10, the stress (N/mm2) in concrete is

  2. A.
    11
    B.
    9
    C.
    7
    D.
    5

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question. Let us discuss.