Home / Civil Engineering / Highway Engineering :: Discussion

Discussion :: Highway Engineering

  1. To indicate proper control of consistency of a freshly mixed concrete for pavement construction, the slump should be between

  2. A.
    3 to 5 cm
    B.
    4 to 6 cm
    C.
    5 to 7 cm
    D.
    7 to 10 cm
    E.
    10 to 12 cm

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question. Let us discuss.


Be The First To Comment