Home / Civil Engineering / Highway Engineering :: Discussion

Discussion :: Highway Engineering

  1. In the penetration macadam construction, the bitumen is

  2. A.

     Sprayed after the aggregates are spread and compacted

    B.

     Premixed with aggregates and then spread

    C.

     Sprayed before the aggregates are spread and compacted

    D.

     None of the above

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    Explanation Not Provided


Be The First To Comment