  1. Select the incorrect statement.

  2. A.

     Stop or red time of a signal is the sum of go and clearance intervals for the cross flow.

    B.

     Go or green time of a signal is the sum of stop and clearance intervals for the cross flow.

    C.

     Clearance time is generally 3 to 5 seconds.

    D.

     The cycle length is normally 40 to 60 seconds for two phase signals.

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided