- The uplift pressure on the face of a drainage gallery in a dam is taken as
A.
hydrostatic pressure at toe |
B.
average of hydrostatic pressure at toe and heel |
C.
two-third of hydrostatic pressure at toe plus one-third of hydrostatic pressure at heel |
D.
none of the above |
Answer : Option C
Explanation :
Explanation Not Provided