  1. If a 0.7% upgrade meets a 0.65% downgrade at a summit and the permissible rate of change of grade per chain length is 0.10%, the length of the vertical curve, is

  2. A.

    10 chains

    B.

    12 chains

    C.

    14 chains

    D.

    16 chains

    Answer : Option C

    Explanation :

    No answer description available for this question.