- For under water concreting.
A.
At least 10 percent more cement is required as compared to dry conditions |
B.
The volume of coarse aggregates shall not be less than one and half times and not more than twice that of fine aggregate |
C.
De-watering by pumping is not done or until 24 hours thereafter |
D.
All the above |
Answer : Option D
Explanation :
Explanation Not Provided