  1. In drawing AOA networks and making time computations, the following processes are involved :
    1. Activity listing
    2. Work breakdown structure
    3. Activity time allotment
    4. Consideration of available resources for each activity
    5. Activity dependencies
    6. Float computations
    7. Backward path computation
    8. Project duration
    9. Forward path computation
    What is the correct sequence of the processes given above ?

  2. A.
    1, 2, 4, 3, 9, 7, 5, 6, 8
    B.
    2, 1, 4, 3, 5, 9, 8, 7, 6
    C.
    4, 1, 3, 2, 9, 5, 7, 8, 6
    D.
    Any sequence can be followed but 6 and 7 will be the last two ones

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question. Let us discuss.


Be The First To Comment