  1. The normal duration and normal cost of an activity are 10 days and Rs 350/- respectively. The cost slope is Rs 75/- per day. If the crash duration is 8 days, then what is the crash cost of the activity ?

  2. A.
    Rs 400/-
    B.
    Rs 500/-
    C.
    Rs 600/-
    D.
    None of these

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question. Let us discuss.