  1. In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?

  2. A.
    Beta distribution
    B.
    Poisson distribution
    C.
    Normal distribution
    D.
    Log-normal distribution.

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    No answer description available for this question. Let us discuss.