  1. The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is

  2. A.
    8 days
    B.
    9 days
    C.
    10 days
    D.
    11 days

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question. Let us discuss.