  1. Consider the following statements :
    A critical activity in a CPM network has
    1. The longest duration of all activities
    2. zero total float
    3. zero for float
    4. The shortest duration of all activities
    which one of the statements given above are correct ?

  2. A.
    1 and 2
    B.
    1 and 3
    C.
    2 and 3
    D.
    3 and 4

    View Answer

    Workspace

    Answer : Option A

    Explanation :