Home / Civil Engineering / UPSC Civil Service Exam Questions :: Discussion

Discussion :: UPSC Civil Service Exam Questions

  1. In "full face" method of constructing tunnel, the first operation relates to

  2. A.
    removal to bottom portion
    B.
    excavation of one drift in the centre
    C.
    removal of top portion
    D.
    excavation being done along the perimeter

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question. Let us discuss.