Home / Civil Engineering / UPSC Civil Service Exam Questions :: Discussion

Discussion :: UPSC Civil Service Exam Questions

  1. In the network given above, the critical path of activities is in the given figure

  2. A.
    A-C-H
    B.
    B-E-F-H
    C.
    A-D-E-F-H
    D.
    A-D-E-G

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question. Let us discuss.


Be The First To Comment