  1. What does the critical path in PERT represent ?
    1. The shortest path for the earliest completion of the project.
    2. The longest path of the network from the initial to final event,

  2. A.
    1 only
    B.
    2 only
    C.
    Both 1 and 2
    D.
    Neither 1 nor 2

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    No answer description available for this question. Let us discuss.