Consider the following statements :
The critical path in a network plan of a project
1. helps in planning efficient time schedule
2. indicates the shortest path in time
3. helps in crashing the project judiciously
4. helps in encouraging discipline in execution.
Of these statements :
A.
1, 3 and 4 are correct
|
B.
1, 2, 3 and 4 are correct
|
C.
1 and 4 are correct
|
D.
2 and 3 are correct
|