  1. What is the value of camber rate that should be provided in case of WBM pavement surface in an area of heavy rainfall ?

  2. A.
    1 in 30
    B.
    1 in 48
    C.
    1 in 60
    D.
    1 in 72

    View Answer

    Workspace

    Answer : Option A