  1. In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is

  2. A.
    12 days
    B.
    14 days
    C.
    15 days
    D.
    17 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question. Let us discuss.