  1. What is the time by which the completion of an activity can be delayed without affecting the start of succeeding activities, called ?

  2. A.
    Total float
    B.
    Interfering float
    C.
    Independent float
    D.
    Free float

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question. Let us discuss.