  1. The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation ?

  2. A.
    12, 3
    B.
    11, 4
    C.
    11,
    D.
    10, 16

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question. Let us discuss.