Home / Civil Engineering / UPSC Civil Service Exam Questions :: Discussion

Discussion :: UPSC Civil Service Exam Questions

  1. When power shovels are operated under different site conditions (in terms of material handled), what is the correct sequence in the increasing order of the ouput for the following materials ?
    1. Well - blasted rock
    2. Hard and tough clay
    3. Poorly blasted rock
    4. Moist loam or sand
    Select the correct answer using the code given below :

  2. A.
    1 - 2 - 3 - 4
    B.
    1 - 4 - 3 - 2
    C.
    4 - 2 - 3 - 1
    D.
    4 - 3 - 1 - 2

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question. Let us discuss.