Home / Civil Engineering / Waste Water Engineering :: Discussion

Discussion :: Waste Water Engineering

  1. Pick up the correct statement from the following :

  2. A.

    The maximum rate of storm run off is called peak drainage discharge

    B.

    Rational method of estimating peak run off, may be used precisely for areas less than 50 hectares

    C.
    The period after which the entire area starts contributing to the run off, is called the time of concentration
    D.
    The time required by water to reach the outlet of a catchment from the most remote point, is called time of concentration
    E.

    All the above.

    View Answer

    Workspace

    Answer : Option E

    Explanation :

    No answer description available for this question.


Be The First To Comment