Home / Civil Engineering / Waste Water Engineering :: Discussion

Discussion :: Waste Water Engineering

  1. The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is

  2. A.

    1 in 100 upward

    B.

    1 in 500 upward

    C.

    1 in 100 downward

    D.

    1 in 503 upward.

    View Answer

    Workspace

    Answer : Option C

    Explanation :

    No answer description available for this question.