  1. Out of the following constraints, select the one which doesn't require start or finish date to be added in order to schedule a task in MS Project.
  2. A.
    SNET
    B.
    FNLT
    C.
    ALAP
    D.
    MFO

    View Answer

    Workspace

    Answer : Option C