Discussion :: Microsoft Project
- How to set work time exception in Project?
A.
Select the project and change the working time
|
B.
On the calendar choose the day you want to change
|
C.
Click the exception tab to display it, it will show a column with the name cell in a blank row, type a name for the exception and press enter
|
D.
All of these
|
Answer : Option D
Explanation :
Be The First To Comment