  1. A(n) __________ determines how tasks and resources assigned to these tasks are scheduled.
  2. A.
    Schedule
    B.
    Exception plan
    C.
    Calendar
    D.
    Resource pool

    View Answer

    Workspace

    Answer : Option A

    Explanation :