  1. Which of the following parameter in multiple counter plan defines the call date for the order in relation to the calculated planned date and thereby also the basic start date for the maintenance order?
  2. A.
    Operation type
    B.
    Scheduling period
    C.
    Cycle modification factor
    D.
    Preliminary buffer

    View Answer

    Workspace

    Answer : Option D

    Explanation :