  1. Which of the following determines the maintenance package will be performed if two maintenance packages are due at the same time?
  2. A.
    Cycle Length
    B.
    Offset
    C.
    Hierarchy
    D.
    Initial Buffer

    View Answer

    Workspace

    Answer : Option C

    Explanation :