Home / CSE MCQs / SAP PP :: Discussion

Discussion :: SAP PP

  1. Planning can create the following after MRP run
  2. A.
    Planned Orders
    B.
    Production Orders
    C.
    Purchase Orders
    D.
    Schedule Lines

    View Answer

    Workspace

    Answer : Option A

    Explanation :