- The Individual / Collective indicator in the material Master determines
A.
Whether a component is procured for a special customer requirement in the individual segment
|
B.
Requirement quantities of dependent materials are grouped together during MRP run
|
C.
The Material Requirement Planning
|
D.
The Special Procurement
|
Answer : Option C
Explanation :