  1. When scheduling a routing in the SAP ECC system, which of the following time elements is a interoperation time?
  2. A.
    Safety time
    B.
    Float before production
    C.
    Processing time
    D.
    Setup time

    View Answer

    Workspace

    Answer : Option B

    Explanation :