Discussion :: SAP PS
- What are the pre-requisites for distributing work to HR Resources?
A.
In Customizing for the Project System, you must have defined profiles for workforce planning in Resources
|
B.
Assigned work centers to the internally processed activities
|
C.
Assigned one or more labor capacity to a work center
|
D.
Both A and B
|
Answer : Option D
Explanation :