  1. If you are planning a project in SAP PS using CJ40 Work Breakdown Structure, at which of the following locations can you find the values used in the planning?
  2. A.
    RPSCO table
    B.
    COSS & COSP tables
    C.
    BPEJ table
    D.
    None of the mentioned

    View Answer

    Workspace

    Answer : Option B

    Explanation :