  1. The latest time that the event can be delayed without delaying the completion of the entire project in PERT chart is:

  2. A.
    earliest allowable time
    B.
    latest allowable time
    C.
    earliest pass
    D.
    latest pass
    E.
    None of the above

    View Answer

    Workspace

    Answer : Option B

    Explanation :