Home / CSE / System Analysis and Design :: Discussion

Discussion :: System Analysis and Design

  1. Which of the following systems implementation approaches should be used if you want to run the old system and the new system at the same time for a specified period?

  2. A.
    direct
    B.
    pilot
    C.
    phased
    D.
    parallel
    E.
    None of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    No answer description available for this question.


Be The First To Comment