Home / EEE / Power Plant Engineering in EE :: Discussion

Discussion :: Power Plant Engineering in EE

  1. For forced draught system, the function of chimney is mainly

  2. A.

     to produce draught to accelerate the combustion of fuel

    B.

     to discharge gases high up in the atmosphere to avoid hazard

    C.

     to reduce the temperature of the hot gases discharged

    D.

     none of the above

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    Explanation Not Provided