Discussion :: Industrial Engineering and Prod'n Mgmt
- The essential condition for the decompression of an activity is that
A.
The project time should change due to decompression |
B.
After decompression the time of an activity invariably exceeds its normal time |
C.
An activity could be decompressed to the maximum extent of its normal time |
D.
None of the above |
Answer : Option C
Explanation :
The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time