  1. An optimum project schedule implies

  2. A.

     Optimum utilization of men, machines and materials

    B.

     Lowest possible cost and shortest possible time for project

    C.

     Timely execution of project

    D.

     To produce best results under given constraints

    View Answer

    Workspace

    Answer : Option B

    Explanation :

    An optimum project schedule implies Lowest possible cost and shortest possible time for project