  1. The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

  2. A.

     Early finish

    B.

     Early start

    C.

     Late start

    D.

     Late finish

    View Answer

    Workspace

    Answer : Option A

    Explanation :

    The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early finish