- A dummy activity
A.
Is artificially introduced |
B.
Is represented by a dotted line |
C.
Does not require any time |
D.
All of the above |
Answer : Option D
Explanation :
A dummy activity is a simulated activity of sorts, one that is of a zero duration and is created for the sole purpose of demonstrating a specific relationship and path of action on the arrow diagramming method.