  1. A dummy activity

  2. A.

     Is artificially introduced

    B.

     Is represented by a dotted line

    C.

     Does not require any time

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    A dummy activity is a simulated activity of sorts, one that is of a zero duration and is created for the sole purpose of demonstrating a specific relationship and path of action on the arrow diagramming method.