  1. A milestone chart

  2. A.

     Shows the inter dependences of various jobs

    B.

     Depicts the delay of jobs, if any

    C.

     Points outgoing ahead of schedule of jobs, if any

    D.

     None of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    A Milestone Chart focuses on planned significant events scheduled to occur at specific times in the program