- Earliest finish time can be regarded as
A.
Earliest start time + duration of activity |
B.
Earliest start time duration of activity |
C.
Latest finish time + duration of activity |
D.
Latest finish time duration of activity |
Answer : Option A
Explanation :
Earliest finish time can be regarded as Earliest start time + duration of activity