Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: Discussion

Discussion :: Industrial Engineering and Prod'n Mgmt

  1. Which of the following statement is correct?

  2. A.

     When slack of an activity is zero, it falls only on critical path.

    B.

     CPM technique is useful to minimize the direct and indirect expenses.

    C.

     Critical path of a net work represents the minimum time required for completion of project.

    D.

     All of the above

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    -When slack of an activity is zero, it falls only on critical path.
    - CPM technique is useful to minimize the direct and indirect expenses.
    - Critical path of a net work represents the minimum time required for completion of project.