Discussion :: Industrial Engineering and Prod'n Mgmt
- Which of the following statement is correct?
A.
When slack of an activity is zero, it falls only on critical path. |
B.
CPM technique is useful to minimize the direct and indirect expenses. |
C.
Critical path of a net work represents the minimum time required for completion of project. |
D.
All of the above |
Answer : Option D
Explanation :
-When slack of an activity is zero, it falls only on critical path.
- CPM technique is useful to minimize the direct and indirect expenses.
- Critical path of a net work represents the minimum time required for completion of project.
Be The First To Comment