Home / Mechanical Engineering / Industrial Engineering and Prod'n Mgmt :: Discussion

Discussion :: Industrial Engineering and Prod'n Mgmt

  1. The critical path of a network represents

  2. A.

     The minimum time required for completion of project

    B.

     The maximum time required for completion of project

    C.

     Maximum cost required for completion of project

    D.

     Minimum cost required for completion of project

    View Answer

    Workspace

    Answer : Option A

    Explanation :


    The critical path of a network represents The minimum time required for completion of project