- The critical path of a network represents
A.
The minimum time required for completion of project |
B.
The maximum time required for completion of project |
C.
Maximum cost required for completion of project |
D.
Minimum cost required for completion of project |
Answer : Option A
Explanation :
The critical path of a network represents The minimum time required for completion of project